Requests for service that involve a design drawing and cost estimate. |
 |
The applicant must submit a completed SJWC Form 40 Questionaire along with improvement plans a construction schedule, underground piping plans, and an engineering deposit. A file is assembled and a job number is assigned to the project. |
 |
Fire Department requirements are confirmed. |
 |
The file is routed to the SJWC Engineering Department for preparation of a construction drawing and a cost estimate. A hydraulic review is done by SJWC and backflow requirements determined. |
 |
Upon completion of engineering, the file is returned for the preparation of a construction agreement and a cover letter that explains the procedure to be follwed to process the job for construction. |
 |